Update August 6, 2021-
On Monday, August 9th (rain date of Tuesday, August 10th), Parisi will be tying into the sanitary sewer at the end of Laufenberg. Part of this process requires to have the core drill truck use Laufenberg Blvd to access the manhole.
This should only take a few hours.
If you have any questions about this project, you can email Village Administrator Bill Chang: bchang@cross-plains.wi.us
*****
Update July 22, 2021-
Construction is scheduled to start for Creek Crossing at St.Francis on Monday, July 26, 2021. All construction vehicle access will only be allowed from North Hill Point Road. No construction vehicles are permitted to access the site from Laufenberg Blvd. until the contractor is ready to connect Laufenberg Blvd at a later point in the construction schedule. Work at this site is expected to last until the end of October.
Any questions or concerns regarding this project should be emailed to Bill Chang: bchang@cross-plains.wi.us.